Update from Thames Water on the Sewer Repairs as of Friday 23/5/14,
The base of the new manhole has been laid and connected, this mean that the tanker is nor longer required 24/7 and has been stood down. The dewatering pump that is working next to the hole is still required until the hole has been backfilled. They now need other utility companies on site to check their cables and pipes as the back fill is carried behind the support sheets Thames Water have in place. This should be done on Tuesday then Thames can continue their work building up the manhole. Once this has been completed Thames will arrange to have the sewer in Well Lane cleaned through to make sure no residue from the works and collapse are in the system.